SECI has announced winners for its 1.5 GW / 6 GWh assured peak power tender — a four-hour firm renewable block — discovering a tariff of ₹5.99/kWh. ACME Solar took 300 MW of the round. Reported between 22 and 25 August 2026, the auction is awarded and now moves toward power purchase agreements.

Published 22 August 2026 · Last updated 25 August 2026 · 1 min read · By Alpha Devraj ESS Research Desk

India’s largest four-hour peak-power round to date, tracked as part of our tender tracker.

Award Mercom India / pv magazine India · 22–25 Aug 2026

SECI assured peak power auction

Power

1,500 MW

Energy

6,000 MWh

Duration

4 hr

Tariff

₹5.99 /kWh

Discharge signature — long-duration, runs 4h of 8h at rated power

Tendered Awarded Contracted Live

Six gigawatt-hours of four-hour peak supply cleared at ₹5.99/kWh — the clearest national price signal yet for long-duration firmed renewables.

Mercom India ↗

What it means

Six thousand megawatt-hours behind 1,500 MW is a four-hour, long-duration block — storage sized to carry the evening peak rather than trim it, the distinction we set out in 2-hour vs 4-hour BESS explained. At this scale the auction is less a project than a price benchmark: ₹5.99/kWh is a blended energy tariff for delivered peak power, so it is not directly comparable with the capacity charges (₹ per MW per month) discovered in standalone battery tenders.

ACME Solar’s 300 MW is one fifth of the round, which tells you the capacity was spread across several developers rather than concentrated — a healthy sign for competitive tension in the assured-peak and FDRE framework that now anchors central procurement under India’s storage policy.

As of this briefing the round is awarded; power purchase agreements and project locations follow.

Bidding into an assured-peak round? Talk to our team, or model the storage economics first.