Skip to content
Alpha Devraj — Energy Storage Systems

Policy & tenders

Can battery storage be used as a transmission asset in India?

Yes. Indian rules let a battery take the legal status of its owner, so a transmission licensee can own grid-side storage and recover its cost through transmission charges. CERC's tariff amendment notified on 1 December 2025 explicitly permits licensees to install storage for reliability enhancement and transmission deferral.

Published 18 September 2026 · Last updated 18 September 2026 · 9 min read · By Alpha Devraj ESS Research Desk

On this page

Almost every conversation about batteries in India starts from the same assumption: a battery is a kind of generator. It buys cheap power, sells expensive power, and its business case is the gap between the two.

That assumption quietly excludes the use that may matter most to the grid. A battery can also be a piece of wires — a substitute for the line, transformer or substation that would otherwise have to be built. In that role it does not sell anything. It earns the way a transformer earns: by being in the rate base, recovered through transmission charges, and by saving the network the cost of an upgrade it no longer has to make.

India’s rules now allow exactly that, and the first projects are in the market.

The starting point is a piece of drafting that sounds dry and turns out to be the whole story.

Under Rule 18 of the Electricity Rules, as amended by the Electricity (Amendment) Rules, 2022, an energy storage system is treated as part of the power system — and it takes its legal status from its owner. If a generating company owns and co-locates it, the storage has the status of generation. If a transmission licensee owns it, the storage has the status of transmission. If a distribution licensee owns it, distribution.

Two consequences follow, and both are important:

  • The same hardware is three different assets. A 300 MWh container yard does not change physically when a transmission company buys it instead of a developer. What changes is which regulatory box it sits in, who pays for it, and what it is allowed to earn.
  • Standalone storage is delicensed. A developer building storage on its own does not need a generation licence, which removed one of the early obstacles to the sector getting started.

So the answer to “can a battery be a transmission asset in India” was, in principle, yes from 2022 onward. What was missing was the tariff machinery to actually recover the cost. That arrived at the end of 2025.

What CERC’s December 2025 amendment changed

The Central Electricity Regulatory Commission (CERC) — the regulator for interstate transmission and central generation — notified its Terms and Conditions of Tariff (Second Amendment) Regulations on 1 December 2025. It introduced a term worth knowing: the Integrated Energy Storage System (IESS), meaning storage co-located with a generating station or a transmission system and connected to a common bus, used for grid reliability, transmission deferral, or flexible operation.

The substance for our purposes:

  • Transmission licensees are explicitly empowered to install grid-side storage for reliability enhancement and transmission deferral. This is the sentence that turns a theoretical legal status into a buildable asset class.
  • Transmission-side revenues reduce annual transmission charges. If the storage earns anything, the benefit flows back to the users who are paying for the network, not to the licensee as profit.
  • Gains are shared 50:50 between the generator and the beneficiaries, after fixed and variable storage costs are met, where storage sits at a generating station.
  • Batteries get a 12-year depreciation life, which for the first time gives a lender and a regulator a common number to work from.
  • Performance norms are specified: minimum 85% round-trip efficiency, minimum 90% availability, and 5% auxiliary consumption.
  • A regulatory sandbox allows costs up to 0.5% of annual fixed cost, or ₹100 crore, to be spent on testing innovations.
  • Supplementary tariff filings must be made within 30 days of commercial operation.

There is also a related set of proposals in motion — CERC’s fifth amendment to the interstate transmission connectivity rules, aimed at easing connectivity and reducing the bank guarantee burden for storage projects. Those are proposals, so treat them as direction of travel rather than settled law.

The mechanism: why a battery can stand in for a line

The logic is easier to see than to describe. A transmission element — a line, a transformer, an interconnecting bay — is sized for its worst few hours of the year. For the remaining several thousand hours it is comfortably within its rating. When load growth pushes those worst hours past the limit, the conventional answer is to build more capacity, sized again for a handful of hours.

A battery placed downstream of the constraint attacks the problem from the other end. During the evening peak it discharges locally, so the power does not have to travel across the constrained element at all. During the solar middle of the day, when the same corridor has spare headroom, it recharges. The peak flow comes down; the upgrade can wait.

Loading on a constrained corridor across one dayOver the limit — upgrade triggered050%100%125%128% at 19:0096% — inside ratingcharges into midday headroom00:0012:0024:00Corridor loading without storageWith storage downstream of the constraintIllustrative shape, not a specific corridor.
A battery downstream of a constrained corridor does not move energy past the bottleneck — it shifts energy in time at the far end, so peak flow across the limiting element stays inside its rating.

Note what the green line does at midday: it goes up. Charging adds load to the corridor. That is the honest version of this story — storage does not reduce energy flow, it reschedules it into the hours when the network has room. Which is also why the siting study matters more than the battery specification, and why connectivity and general network access rules determine whether a given location is even usable.

Why timing is the real argument

On cost alone, a battery is not automatically cheaper than conductor. Where it wins is the calendar.

Conventional line or transformer upgradeStorage at the constrained substation
Lead timeSeveral years — survey, right-of-way, approvals, constructionMonths. POWERGRID’s tenders specify a 15-month completion period
Land and right-of-wayA corridor across many landholdingsA compact yard inside the existing substation boundary
Sizing riskFixed at build. Oversize and it sits idle; undersize and you rebuildModular. Containers can be added as the constraint grows
If load growth disappointsStranded assetRelocatable, or redeployed to another service
Useful lifeDecades12 years in CERC’s depreciation schedule; augmentation extends it
Other benefitsCapacity onlyVoltage support, frequency response, ride-through during disturbances

The asymmetry in the first row is the point. A deferral is valuable even if the line eventually gets built, because it buys the years in which load growth becomes clearer and the upgrade can be sized to what actually happened rather than to a forecast.

The last row matters too. A battery installed for transmission deferral is also, incidentally, a fast-responding resource that helps with grid stabilisation on every ordinary day. That stacking is part of why the economics work, though under CERC’s framework much of that benefit flows to network users through reduced transmission charges rather than to the asset owner.

What is actually being built

This has moved past consultation papers.

POWERGRID has tendered a 150 MW / 300 MWh system at the 400/220 kV Kalikiri substation in Andhra Pradesh. It is part of a larger 1,000 MW / 2,000 MWh programme in that state, procured through tariff-based competitive bidding with viability gap funding routed through the Power System Development Fund (PSDF).

Separately, POWERGRID has floated two tenders totalling 750 MW / 2,000 MWh — a 500 MW / 1,000 MWh two-hour system under Category A, and a 250 MW / 1,000 MWh four-hour system under Category B. The structure is build, own, operate, with POWERGRID procuring on behalf of its wholly owned subsidiary POWERGRID Energy Services Limited (PESL), which retains ownership. The completion period is 15 months, followed by a 12-year comprehensive maintenance obligation.

Read those two Category definitions together and you can see the framework doing its job. A two-hour system is a capacity and peak-relief asset. A four-hour system at the same MW rating is an energy-shifting asset. A transmission planner choosing between them is making a duration decision of exactly the kind we cover in two-hour versus four-hour storage, except the driver is corridor loading rather than a tariff spread. Live tenders of this kind, as they appear, are listed in our tender tracker.

The gaps a developer should know about

Being honest about what is not yet settled:

  • There is no separate “transmission deferral” product you can bid into. The enabling status and the tariff treatment exist. What does not exist is a standing market where a developer offers deferral value and gets paid a defined price for it. You participate by winning a licensee’s tender.
  • Deferral value is not paid to the developer. The saving accrues to the network and its users. A developer’s return comes from the tender’s own capacity payment, not from a share of the avoided line.
  • Siting is decided by someone else. The commercial value of this asset class is overwhelmingly locational, and the location is chosen by the licensee’s planning studies. That narrows the addressable opportunity considerably compared with merchant storage.
  • Interstate and intrastate rules differ. CERC’s framework governs interstate transmission. A state transmission utility works under its own State Electricity Regulatory Commission, and the tariff treatment of licensee-owned storage varies. Our state-by-state policy guides are the place to start for a specific state.

Policies, tender terms and tariff regulations in this area change by notification — CERC’s connectivity amendments were still at proposal stage as of September 2026 — so verify current terms against the latest CERC, Ministry of Power and state commission notifications before committing to a bid or a design.

What this means for you

If you are a transmission or distribution licensee, the regulatory permission you were waiting for is in place, and the interesting work is now planning rather than policy. The question to run through your system studies is which constrained elements have a peak sharp enough and narrow enough that a two- to four-hour battery meaningfully defers the upgrade. Elements that are loaded for twelve hours a day are a wires problem; elements that breach their rating for three hours on a hundred evenings a year are a storage problem.

If you are a developer, treat this as a distinct market from merchant and tender-based storage rather than a variation of it. The counterparty is a licensee, the contract is long and availability-based, the revenue is a capacity payment rather than a spread, and the availability norm — 90% under CERC’s regulation — is what your operations and maintenance plan has to be built around. Container-class systems such as the ADESS 6500 are the relevant hardware at this scale, arrayed into grid blocks sized to the corridor rather than to a tariff arbitrage.

If you are a large industrial or C&I buyer, this mostly explains something you have experienced rather than something you will buy. If your connection request has been held up because the upstream network is constrained, licensee-owned storage is one of the tools that may unblock it — and separately, storage on your own side of the meter is the fastest route to living within a constrained connection instead of waiting for it to be reinforced.

If a network constraint, a connection delay or an evening peak is the problem you are actually trying to solve, the useful first step is a load and constraint profile rather than a product choice. Talk to our team and we will work through what the site genuinely needs.

Policy and tender snapshot as of September 2026. Indian storage regulation is moving quickly through CERC, Ministry of Power and state commission processes; verify current notifications before design, bidding or investment decisions.

Frequently asked questions

What does "storage as a transmission asset" actually mean?

It means the battery is owned by the transmission licensee and treated as part of the wires business rather than as a generator selling power. Its cost sits in the transmission tariff and is recovered through transmission charges paid by users of the network, in the same way a transformer or a reactor is. It is not bidding into the market to earn an energy margin.

How does a battery defer a transmission upgrade?

A line or transformer is sized for its worst few hours of the year. If a battery sitting downstream of the constraint discharges during those hours, the flow across the constrained element stays under its limit, and the upgrade can be postponed. The battery recharges when the same corridor has spare headroom, typically in the solar middle of the day or overnight.

Is this the same as a virtual transmission line?

It is the same family of idea — using something other than conductor to solve a network problem, often called a non-wires alternative. A battery does not physically move energy from one place to another the way a line does. It shifts energy in time at one location so that less has to move through the constrained element at the moment it matters.

Can a developer build this, or only POWERGRID and state transmission companies?

Both, but with different wrappers. A licensee can own the asset directly and recover it through transmission charges. More commonly, a licensee tenders the project and a developer builds, owns and operates it under a long contract — POWERGRID has used a build, own, operate structure through its subsidiary POWERGRID Energy Services Limited, with the developer also carrying maintenance for over a decade.

Does a transmission-asset battery earn market revenue too?

Sometimes, and the regulation anticipates it. CERC has provided for gains after fixed and variable storage costs to be shared, and for transmission-side revenues to reduce annual transmission charges — so a surplus flows back to network users rather than to the licensee. A developer should read the specific tender for how any upside is treated rather than assume a merchant tail.

Let's talk storage

Want these numbers for your site?

Send a bill or a load profile — we model it and tell you straight.