The largest single battery procurement on our tender tracker so far. It buys equipment, not a finished project.
NGEL battery containers + grid-forming PCS supply
Programme power
10 GW
Deliverable energy
40.58 GWh
Duration
4 hr
Discharge signature — long-duration, runs 4h of 8h at rated power
Seven blocks of 4.56 to 6.80 GWh each. Suppliers bid block by block and maintain the systems for 15 years.
ESS News ↗Tender at a glance
| Phase | Blocks (GWh) | Phase total |
|---|---|---|
| Phase 1 | 4.98 · 6.60 · 5.84 | 17.42 GWh |
| Phase 2 | 4.56 | 4.56 GWh |
| Phase 3 | 5.80 · 6.80 · 6.00 | 18.60 GWh |
| Total | 7 blocks | 40.58 GWh |
- Scope: supply LFP containerised battery systems with grid-forming power conversion systems (PCS). The supplier also supervises erection, installation and commissioning up to the PCS output terminals. Energetica India and Power Peak Digest both report this.
- Service: a 15-year long-term service agreement (LTSA) from the commissioning of each project.
- Bidding unit: one complete block is the minimum. Bids for part of a block are rejected (Energetica India). Bidders may quote for one, several or all blocks.
- Bid security (Energetica India): ₹50 crore for up to 5 GWh quoted, ₹100 crore for 5–10 GWh, and ₹200 crore above 10 GWh.
- Eligibility (Energetica India): the main route requires a manufacturer that has supplied at least 4,000 MWh of containerised battery systems through at most 10 orders in three years, including one order of 500 MWh or more. Indian companies with smaller BESS, solar or wind, or industrial-project experience can qualify by teaming with such a manufacturer. They then accept joint and several liability.
- Key dates: bids close on 8 December 2026 at 3:00 PM, and techno-commercial bids open the same day at 3:30 PM (Energetica India). Power Peak Digest also gives 8 December and says the tender document is free of cost. Confirm dates and any corrigenda on NGEL’s e-procurement portal.
What it means
NGEL is buying the batteries and grid-forming inverters itself and running the civil works and balance of system as separate EPC packages. Its 250 MW / 1,000 MWh Kayamkulam BoS tender is the first example. For cell and pack makers, 40.58 GWh is about 2.5 times SECI’s 4 GW / 16 GWh standalone tender. The grid-forming requirement matters too. Our grid-forming inverters explainer covers why utilities now ask for it, and our LFP vs NMC guide covers the chemistry choice.
Planning a supply or consortium bid? Talk to our bid desk.