What is NGEL's 250 MW / 1,000 MWh Kayamkulam battery storage tender?

NTPC Green Energy has invited bids for the balance-of-system package of a 250 MW / 1,000 MWh battery at NTPC Kayamkulam in Kerala. The contractor builds everything except the battery containers and grid-forming PCS, which NGEL supplies, and runs O&M for five years. Renewable Watch reports bids close on 11 December 2026.

Published 14 November 2026 · Last updated 14 November 2026 · 1 min read · By Alpha Devraj ESS Research Desk

A 1 GWh EPC package on our tender tracker, and the first site to show how NGEL’s owner-supplied battery model works.

Tender Renewable Watch · 12 Nov 2026

NGEL Kayamkulam BESS — balance of system

Power

250 MW

Energy

1,000 MWh

Duration

4 hr

Discharge signature — long-duration, runs 4h of 8h at rated power

Tendered Awarded Built Live

One four-hour block at 220 kV. NGEL supplies the batteries and PCS; the contractor builds and runs the rest.

Renewable Watch ↗

Tender at a glance

  • Capacity: a single 250 MW / 1,000 MWh block, integrated at 220 kV, with a minimum design life of 15 years (Renewable Watch, Power Peak Digest).
  • Owner-supplied equipment: NGEL supplies the battery DC containers and grid-forming PCS free of cost. Renewable Watch says their nameplate rating will be 15% above the specified AC discharge capacity.
  • Contractor scope: turnkey design, engineering, supply, construction, testing and commissioning. This covers a new 220 kV air-insulated switchyard, power transformers, pooling switchgear, EMS and SCADA, protection, auxiliary power and fire-fighting. It also includes customs clearance and transport of the containers and PCS from an Indian port, civil works, and grid-compliance and power-quality studies (Renewable Watch).
  • O&M: comprehensive O&M for five years from commissioning. A separate maintenance contract for the battery and PCS is arranged by the owner (Power Peak Digest).
  • Excluded: the LILO of the existing 220 kV line to the switchyard is a separate package (Power Peak Digest).
  • Deadline: online bids close on 11 December 2026 (Renewable Watch and Power Peak Digest). Confirm on NGEL’s e-procurement portal.

What it means

The batteries for this site will come from NGEL’s 10 GW / 40 GWh supply tender, so this package suits EPC firms with switchyard and integration experience rather than cell makers. Four hours of storage at a coastal thermal site gives Kerala evening-peak support. The state’s wider storage rules are in our Kerala BESS policy guide, and the EMS vs BMS explainer covers the control layer the contractor provides.