TrueRE Oriana wins 900 MW/1,800 MWh in Maharashtra; SJVN closes a 265 MW/530 MWh auction — 28 September 2026

TrueRE Oriana Power's 900 MW/1,800 MWh battery win in Maharashtra led India's storage news for 21–25 September 2026. SJVN named the winner of a 265 MW/530 MWh auction, NTPC, MSEDCL and Telangana invited new battery bids, Exide commissioned Phase I of a 6 GWh cell plant, and CERC proposed congestion charges for BESS.

Published 28 September 2026 · Last updated 28 September 2026 · 4 min read · By Alpha Devraj ESS Research Desk

On this page

A busy week after a quiet one. Between 21 and 25 September the feed carried two battery awards with published capacities, three new calls for bids, three manufacturing moves and a cluster of rule changes. Maharashtra appears in every group. Each item with hard numbers now has its own datasheet brief, linked below, and live procurements sit on our tender tracker.

Storage headlines by type, 21–25 September 2026Count of headlines in our feed; the same story from two outlets is counted oncePolicy & regulation6Awards & orders4Tenders & cancellations4Manufacturing3
Storage-relevant headlines in the feed for 21–25 September 2026, grouped by story type. Policy moves outnumbered new tenders, and Maharashtra appeared in every group.

Awards: nearly 2.3 GWh of two-hour storage changes hands

The biggest story of the week was TrueRE Oriana Power’s 900 MW / 1,800 MWh win in Maharashtra, reported by two outlets. SJVN named the winner of its 265 MW / 530 MWh auction. Both are two-hour systems, the peaking shape most Indian buyers are procuring (see our 2-hour vs 4-hour guide).

Tenders: NTPC re-enters Maharashtra, MSEDCL and Telangana go to market

NTPC’s new 400 MWh Maharashtra call came two days after it terminated a 400 MWh contract at its Mouda plant over contractor default. The headlines do not say the new call replaces the old contract. MSEDCL and Telangana both invited battery bids, but neither headline gives a capacity.

Manufacturing: a cell plant goes live, two more gigafactories on paper

Exide’s commissioning is the most concrete item here: it is cell manufacturing, not pack assembly, and it is running. Aare Solar’s Odisha plant has state approval and Solex has announced a plan. Both are still some way from production.

Policy: grid charges, charging rules and two Maharashtra mandates

Regulation made up the largest group. CERC’s proposed congestion charges and a rule change on charging and discharging both affect the revenue a grid battery can earn. Maharashtra drafted storage mandates into both its connectivity (GNA) rules and its rooftop-solar banking rules. For background, see our GNA and storage explainer and the national BESS policy overview.

Tender terms and deadlines change by notification. Always check the current bid documents on the issuing organisation’s portal before acting.


Working out what Maharashtra’s new storage mandates mean for your site? Run the numbers through our BESS savings calculator, or talk to our team for a project-specific read.

Let's talk storage

Want these numbers for your site?

Send a bill or a load profile — we model it and tell you straight.